BREAKDOWN OF UNIT PRICE
Item:020903A. Deduct-Recover Mat-ExSteelStruc
Basis:35cft
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Deduction-Concrete
1.000
cum
943.24
943.24
Sub-Total(C1)
943.24
943.24
Total(1)
943.24
Add over head on Total(1)
3.5 %
33.01
Add Profit on Total(1)
10.0 %
94.32
Total(2)
127.34
Add VAT on Unit Price
5.5 %
7.41
Unit Price
134.75
Say
135
per Cum