BREAKDOWN OF UNIT PRICE
Item:020801. Improved Subgrade
Basis:21189cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
30.000
day
60.00
1800.00
Vibratory Roller (7-10 T)
1.000
day
11500.00
11500.00
Water Tanker
4.000
day
8000.00
32000.00
Dozer
1.000
day
12650.00
12650.00
Sub-Total(A1)
57950.00
96.58
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
4.000
pers
560.00
2240.00
Labour-Un-skilled
26.000
pers
540.00
14040.00
Sub-Total(B1)
16280.00
27.13
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 0.8
670.000
cum
730.00
489100.00
Water
450.000
cum
13.00
5850.00
Sub-Total(C1)
494950.00
824.92
Total(1)
948.63
Add over head on Total(1)
3.5 %
33.20
Add Profit on Total(1)
10.0 %
94.86
Total(2)
128.07
Add VAT on Unit Price
5.5 %
7.45
Unit Price
135.52
Say
136
per Cum