BREAKDOWN OF UNIT PRICE
Item:020604. Pore Water Realease Valve Constru
Basis:5no.
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
5.000
day
60.00
300.00
Vibratory Roller (7-10 T)
0.100
day
11500.00
1150.00
Water Tanker
0.100
day
8000.00
800.00
Trolly Tractor
0.100
day
4000.00
400.00
Pay Loader
0.100
day
14000.00
1400.00
Sub-Total(A1)
4050.00
810.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
2.000
pers
560.00
1120.00
Labour-Un-skilled
3.000
pers
540.00
1620.00
Sub-Total(B1)
2740.00
548.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
1.500
cum
730.00
1095.00
Brick Khoa < 40mm
3.250
cum
3145.00
10221.25
Water
5.000
cum
13.00
65.00
Geotextile
48.000
sqm
128.70
6177.60
Sub-Total(C1)
17558.85
3511.77
Total(1)
4869.77
Add over head on Total(1)
3.5 %
170.44
Add Profit on Total(1)
10.0 %
486.98
Total(2)
657.42
Add VAT on Unit Price
5.5 %
38.26
Unit Price
695.68
Say
696
per No.