BREAKDOWN OF UNIT PRICE
Item:020603. Cladding Layer
Basis:1766cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
4.000
day
60.00
240.00
Vibratory Roller (7-10 T)
0.120
day
11500.00
1380.00
Trolly Tractor
0.120
day
4000.00
480.00
Motor Grader
0.100
day
11500.00
1150.00
Dozer
0.100
day
12650.00
1265.00
Sub-Total(A1)
4515.00
90.30
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Skilled
1.000
pers
580.00
580.00
Labour-Semi-skilled
1.000
pers
560.00
560.00
Labour-Un-skilled
2.000
pers
540.00
1080.00
Sub-Total(B1)
2220.00
44.40
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Soil
50.000
cum
275.00
13750.00
Water
20.000
cum
13.00
260.00
Sub-Total(C1)
14010.00
280.20
Total(1)
414.90
Add over head on Total(1)
3.5 %
14.52
Add Profit on Total(1)
10.0 %
41.49
Total(2)
56.01
Add VAT on Unit Price
5.5 %
3.26
Unit Price
59.27
Say
59
per Cum