BREAKDOWN OF UNIT PRICE
Item:020602. Sand Backfill to Swamp
Basis:5297cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
1.500
day
60.00
90.00
Vibratory Roller (7-10 T)
0.020
day
11500.00
230.00
Dozer
0.020
day
12650.00
253.00
Sub-Total(A1)
573.00
3.82
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Un-skilled
5.000
pers
540.00
2700.00
Sub-Total(B1)
2700.00
18.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
River bed sand (FM<=0.5)
195.000
cum
215.00
41925.00
Sub-Total(C1)
41925.00
279.50
Total(1)
301.32
Add over head on Total(1)
3.5 %
10.55
Add Profit on Total(1)
10.0 %
30.13
Total(2)
40.68
Add VAT on Unit Price
5.5 %
2.37
Unit Price
43.05
Say
43
per Cum