Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:020401. Channel Excavation in Suitable/Un
Basis:3532cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
37.000
day
60.00
2220.00
Sub-Total(A1)
2220.00
22.20
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
7.000
pers
560.00
3920.00
Labour-Un-skilled
25.500
pers
540.00
13770.00
Sub-Total(B1)
17690.00
176.90
Total(1)
199.10
Add over head on Total(1)
3.5 %
6.97
Add Profit on Total(1)
10.0 %
19.91
Total(2)
26.88
Add VAT on Unit Price
5.5 %
1.56
Unit Price
28.44
Say
28
per Cum