BREAKDOWN OF UNIT PRICE
Item:010101. Traffic Protection, Detour Maint
Basis:10no.
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mobile Generator 1-3KVA
0.030
no.
22800.00
684.00
Flashing Light-Main Power
0.140
no.
1200.00
168.00
Flood Ligfht-Pole Mounted
0.140
no.
2300.00
322.00
Traffic Sign with Pole
0.140
no.
9200.00
1288.00
Sub-Total(A1)
2462.00
246.20
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Foreman
30.000
pers
850.00
25500.00
Labour-Semi-skilled
60.000
pers
560.00
33600.00
Labour-Un-skilled
90.000
pers
540.00
48600.00
Sub-Total(B1)
107700.00
10770.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic Tape
2.000
Pks
250.00
500.00
Steel Box forTraffic Mana
2.000
Nos
110.00
220.00
Sub-Total(C1)
720.00
72.00
Total(1)
11088.20
Add over head on Total(1)
3.5 %
388.09
Add Profit on Total(1)
10.0 %
1108.82
Total(2)
1496.91
Add VAT on Unit Price
5.5 %
87.12
Unit Price
1584.03
Say
1584
per KmMo