PWD RATE SCHEDULE-2022 Updating..
Click on Code to see the analysis or Go Home Profit=10%, Overhead=3.5%, VAT=7.5%
17 LIME TERRACING, ROOF TOP WATER PROFFING FOR GARDEN & SWIMMIN
Code Item Unit Cost(Tk.) Unit Rate(Tk.)
170101 Polymer Cemetwater proofing-1.5mm sqm
761.00
934
1701021 Waterproofing roof without mesh sqm
905.00
1110
1701022 Waterproofing roof with fibermesh sqm
1008.00
1237
1702 Gravel Pack with pea-gravel cum
4194.00
5146
1702011 Gravel pack Addl floor cum
159.00
195
1703 Waterproof plaster on roof top sqm
1115.00
1368
1704 Lime Terracing (7:2:2) -100mm cum
15568.00
19102
1704011 Lime Terracing addl floor cum
106.00
130
170501 Ferrocement Treatment-Waterprof sqm
1337.00
1641
170502 Ferrocement for Heat-Waterproofin sqm
1784.00
2189