Return Main Menu

PWD RATE SCHEDULE-2022 Updating..
Click on Code to see the analysis or Go Home Profit=10%, Overhead=3.5%, VAT=5.5%
08 M.S. FABRICATION AND JOINTS IN RC WORKS
Code Item Unit Cost(Tk.) Unit Rate(Tk.)
080101 MS Deformed Bar-Grade- 300 ton
75200.00
90320
080102 MS Deformed Bar-Grade- 400 ton
97420.00
117007
080103 MS Deformed Bar-Grade- 500 ton
111055.00
133384
0802 MS Deformed Bar-Add each floor ton
596.00
716
080301 Thread Coupler-20 mm Bar each
262.00
315
080302 Thread Coupler-25 mm Bar each
417.00
501
080303 Thread Coupler-32 mm Bar each
599.00
719
080401 Press Coupler-16 mm dia bar each
314.00
377
080402 Press Coupler-20 mm dia bar each
433.00
520
080403 Press Coupler-22 mm dia bar each
550.00
661
080404 Press Coupler-25 mm dia bar each
707.00
849
080405 Press Coupler-32 mm dia bar each
1188.00
1427
080501 PVC Water stopper-non centre bulb metr
858.00
1031
080502 PVC Water stopper-centre bulb metr
927.00
1113
0806 Alum Water stopper-RCC vertical metr
313.00
376
080701 Expansion Joint upto 100 mm metr
6044.00
7259
080702 Expansion Joint upto 100-150mm metr
7103.00
8531
080703 Expansion Joint upto 150-200mm metr
8163.00
9804