PWD RATE SCHEDULE-2022 Updating.. | ||||
---|---|---|---|---|
Click on Code to see the analysis or Go Home | Profit=10%, Overhead=3.5%, VAT=5.5% | |||
02 | EXCAVATION, FILLING, SITE DEVELOPMENT AND PALASIDING | |||
Code | Item | Unit | Cost(Tk.) | Unit Rate(Tk.) |
020101 | Earthwork in Excavation-Layout | sqm | 18.00 |
22 |
020102 | Excavate 1.5m depth 10m lead | cum | 152.00 |
183 |
020103 | Excavat addl 0.5m exceed 1.5m dpt | cum | 26.00 |
31 |
020104 | Excavat addl 1m beyond 10 m lead | cum | 4.00 |
5 |
0202 | Bailing out water during excavatn | hr | 374.00 |
449 |
0203 | Driving bamboo post 75mm dia | metr | 74.00 |
89 |
0204 | Wooden Bollah drive in palasiding | metr | 517.00 |
621 |
0205 | Palasiding drum sheet excl post | sqm | 521.00 |
626 |
0206 | Hor bracing wooden bollah-1/2spl | metr | 190.00 |
228 |
020701 | Shore protection-excavation-1.5m | sqm | 581.00 |
698 |
020702 | Shore protection excv beyond 1.5 | sqm | 852.00 |
1023 |
0208 | Geotextile-filled earth protectn | sqm | 180.00 |
216 |
0209 | Remove Sludge, Sand-FM.8=1:10 | cum | 952.00 |
1143 |
021001 | Sand Filling-F.M.=0.5 | cum | 909.00 |
1092 |
021002 | Sand Filling-F.M.=0.8 | cum | 973.00 |
1169 |
021003 | Sand Filling-F.M.=1.2 | cum | 1354.00 |
1626 |
021004 | Sand Filling-F.M.=2.2 | cum | 2732.00 |
3281 |
0211 | Khoa Consolidation-Khoa:LSand=2:1 | cum | 4862.00 |
5840 |
0212 | Khoa Cons-Cement:sand:khoa=1:6:12 | cum | 5726.00 |
6877 |
0213 | Earth Filling with earth availabl | cum | 187.00 |
225 |
0214 | Clearing, disposal earth by truc | cum | 699.00 |
840 |
0215 | Earth Filling by carted by truck | cum | 592.00 |
711 |
021601 | Site Develop by carted by truck | cum | 637.00 |
765 |
021602 | Site Develop by dredging | cum | 421.00 |
506 |
0217 | Mechanical Compaction of Earth | cum | 193.00 |
232 |
021801 | ExcavationPond-Lead 30m,lift-1.5m | cum | 229.00 |
275 |
021802 | ExcavatPond-Addl lift 0.3m,1.5-3m | cum | 8.00 |
10 |
021803 | ExcavatPond-Addl lift 0.3m,3-4.5m | cum | 12.00 |
14 |
021804 | ExcavatPond-Addl lift 0.3m,4.5-6m | cum | 17.00 |
20 |
021805 | ExcavatPnd-Addl lead-03m >30m | cum | 31.00 |
37 |
021901 | Bail-out water-1 cusec DieselPump | hour | 573.00 |
688 |
021902 | Bail-out water-1 cusec ElectrPump | hour | 486.00 |
584 |