Return Main Menu

PWD RATE SCHEDULE-2022 Updating..
Click on Code to see the analysis or Go Home Profit=10%, Overhead=3.5%, VAT=7.5%
02 EXCAVATION, FILLING, SITE DEVELOPMENT AND PALASIDING
Code Item Unit Cost(Tk.) Unit Rate(Tk.)
020101 Earthwork in Excavation-Layout sqm
18.00
22
020102 Excavate 1.5m depth 10m lead cum
152.00
187
020103 Excavat addl 0.5m exceed 1.5m dpt cum
26.00
32
020104 Excavat addl 1m beyond 10 m lead cum
4.00
5
0202 Bailing out water during excavatn hr
374.00
459
0203 Driving bamboo post 75mm dia metr
74.00
91
0204 Wooden Bollah drive in palasiding metr
517.00
634
0205 Palasiding drum sheet excl post sqm
521.00
639
0206 Hor bracing wooden bollah-1/2spl metr
190.00
233
020701 Shore protection-excavation-1.5m sqm
581.00
713
020702 Shore protection excv beyond 1.5 sqm
852.00
1045
0208 Geotextile-filled earth protectn sqm
180.00
221
0209 Remove Sludge, Sand-FM.8=1:10 cum
952.00
1168
021001 Sand Filling-F.M.=0.5 cum
909.00
1115
021002 Sand Filling-F.M.=0.8 cum
973.00
1194
021003 Sand Filling-F.M.=1.2 cum
1354.00
1661
021004 Sand Filling-F.M.=2.2 cum
2732.00
3352
0211 Khoa Consolidation-Khoa:LSand=2:1 cum
4862.00
5966
0212 Khoa Cons-Cement:sand:khoa=1:6:12 cum
5726.00
7026
0213 Earth Filling with earth availabl cum
187.00
229
0214 Clearing, disposal earth by truc cum
699.00
858
0215 Earth Filling by carted by truck cum
592.00
726
021601 Site Develop by carted by truck cum
637.00
782
021602 Site Develop by dredging cum
421.00
517
0217 Mechanical Compaction of Earth cum
193.00
237
021801 ExcavationPond-Lead 30m,lift-1.5m cum
229.00
281
021802 ExcavatPond-Addl lift 0.3m,1.5-3m cum
8.00
10
021803 ExcavatPond-Addl lift 0.3m,3-4.5m cum
12.00
15
021804 ExcavatPond-Addl lift 0.3m,4.5-6m cum
17.00
21
021805 ExcavatPnd-Addl lead-03m >30m cum
31.00
38
021901 Bail-out water-1 cusec DieselPump hour
573.00
703
021902 Bail-out water-1 cusec ElectrPump hour
486.00
596