PWD RATE SCHEDULE-2022 Updating.. | ||||
---|---|---|---|---|
Click on Code to see the analysis or Go Home | Profit=10%, Overhead=3.5%, VAT=7.5% | |||
01 | GENERAL, SITE FACILITIES AND SAFETY | |||
Code | Item | Unit | Cost(Tk.) | Unit Rate(Tk.) |
010101 | Engineers Site Office-10m2 | job | 41000.00 |
50308 |
010102 | Engineers Site Office-15m2 | job | 65500.00 |
80370 |
010103 | Engineers Site Office-38m2 | job | 397000.00 |
487130 |
0101041 | Site Safety-Construction Worker | set | 31500.00 |
38651 |
0101042 | Site Safety-Construction Team | set | 8800.00 |
10798 |
0101043 | Supply and provide first aid-box | each | 13215.00 |
16215 |
0101044 | CCTV / Serviliances facilities | job | 40000.00 |
49081 |
010105 | Project profile signboard-1mx2m | sqm | 2691.00 |
3302 |
010201 | As-built drawing-A2 size-3 sets | tend | 23028.00 |
28256 |
010202 | As-built drawing-A2 size-addl cop | sqm | 270.00 |
331 |
010301 | Project Documentation for monitor | mon | 26485.00 |
32498 |
010401 | Schedule implement by MS Project | tend | 26142.00 |
32077 |
010402 | Schedule update by MS Project | rev | 7742.00 |
9500 |
0105 | Monthly progress meeting at site- | mon | 2000.00 |
2454 |
0106 | Providing Layout | sqm | 27.00 |
33 |
0107 | Mobilization and Demobilization | sqm | 178.00 |
218 |
0108 | Architect Experience more than 5Y | mon | 65198.00 |
80000 |
0109 | Civil Engr Experien more than 10Y | mon | 97797.00 |
120000 |
0110 | Transport for test amd emergency | mon | 57048.00 |
69999 |
011101 | Supervision Lift-6-10th Floor | mon | 14449.00 |
17729 |
011102 | Supervision Lift-10-14th Floor | mon | 17497.00 |
21469 |
011103 | Supervision Lift-15-19th Floor | mon | 20499.00 |
25153 |
011104 | Supervision Lift-20-24th Floor | mon | 23757.00 |
29150 |
011105 | Supervision Lift-25-29th Floor | mon | 26420.00 |
32418 |