01 GENERAL, SITE FACILITIES AND SAFETY
Code Item Unit Cost(Tk.) Unit Rate(Tk.)
010101 Engineers Site Office-10m2 job
41000.00
49243
010102 Engineers Site Office-15m2 job
65500.00
78669
010103 Engineers Site Office-38m2 job
397000.00
476820
0101041 Site Safety-Construction Worker set
31500.00
37833
0101042 Site Safety-Construction Team set
8800.00
10569
0101043 Supply and provide first aid-box each
13215.00
15872
0101044 CCTV / Serviliances facilities job
40000.00
48042
010105 Project profile signboard-1mx2m sqm
2691.00
3232
010201 As-built drawing-A2 size-3 sets tend
23028.00
27658
010202 As-built drawing-A2 size-addl cop sqm
270.00
324
010301 Project Documentation for monitor mon
26485.00
31810
010401 Schedule implement by MS Project tend
26142.00
31398
010402 Schedule update by MS Project rev
7742.00
9299
0105 Monthly progress meeting at site- mon
2000.00
2402
0106 Providing Layout sqm
27.00
32
0107 Mobilization and Demobilization sqm
178.00
214
0108 Architect Experience more than 5Y mon
65198.00
78307
0109 Civil Engr Experien more than 10Y mon
97797.00
117460
0110 Transport for test amd emergency mon
57048.00
68518
011101 Supervision Lift-6-10th Floor mon
14449.00
17354
011102 Supervision Lift-10-14th Floor mon
17497.00
21015
011103 Supervision Lift-15-19th Floor mon
20499.00
24620
011104 Supervision Lift-20-24th Floor mon
23757.00
28534
011105 Supervision Lift-25-29th Floor mon
26420.00
31732