BREAKDOWN OF UNIT PRICE
Item:267406. Septic Tank for 10 Users
Basis:1no.
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
1650.526
Nos.
10.00
16505.26
Sub-Total(A1)
16505.26
16505.26
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
5.888
bag
405.00
2384.64
Cement: CEM-I, 52.5-OPC
12.487
bag
440.00
5494.28
Sub-Total(A2)
7878.92
7878.92
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (FM=0.8)
2.125
cft
16.70
35.49
Sand (F.M.1.2)
47.376
cft
19.00
900.14
Sand (F.M.2.2)
15.608
cft
53.80
839.71
Sub-Total(A4)
1775.34
1775.34
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Manhole Cover-450mm D
2.000
no.
910.00
1820.00
RCC Tee
2.000
no.
450.00
900.00
Sub-Total(B1)
2720.00
2720.00
D1.Prop/Pipe/I-sec/Box
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo prop-use 8 times
21.407
No.
17.25
369.27
Sub-Total(D1)
369.27
369.27
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
1.200
sft
10.00
12.00
Mixer m/c hire charge
0.069
day
1200.00
82.80
Vibrator m/c hire charge
0.139
day
550.00
76.45
Fuel for mixer m/c, vibra
0.069
day
1275.00
87.98
Sub-Total(E1)
259.23
259.23
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Garjan wood use 8 times
1.867
cft
275.00
513.43
Wood for Shutter use 8-ti
6.422
cft
68.75
441.51
Sub-Total(F1)
954.94
954.94
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Sheet/ Plate-use 30 ti
109.173
kg
2.56
279.48
MS Rod 300 grade/ 40 grad
117.967
kg
65.00
7667.86
Sub-Total(F2)
7947.34
7947.34
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
8.162
No.
550.00
4489.10
Mason
2.768
No.
700.00
1937.60
Skilled Labour
2.044
No.
600.00
1226.40
Head Mason
0.483
No.
800.00
386.40
Sub-Total(L1)
8039.50
8039.50
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Breaking 20mm brick-chips
62.433
cft
9.70
605.60
Wood shuttering i/c makin
98.470
sft
18.00
1772.46
Septic Tank-Fill,Clean
0.533
LS
1500.00
799.50
Sub-Total(L2)
3177.56
3177.56
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making form water tight
98.470
sft
3.00
295.41
Sub-Total(L3)
295.41
295.41
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nail and wires, gazals
0.856
kg
70.00
59.92
Curing for 28 days
98.470
sft
4.58
450.99
Sub-Total(M1)
510.91
510.91
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
1.599
No.
550.00
879.45
Sub-Total(M2)
879.45
879.45
Total(1)
51313.13
Add over head on Total(1)
3.5 %
1795.96
Add Profit on Total(1)
10.0 %
5131.31
Total(2)
6927.27
Add VAT on Unit Price
5.5 %
403.17
Unit Price
7330.45
Say
7330
per each