BREAKDOWN OF UNIT PRICE
Item:267403. Septic Tank for 50 Users
Basis:1no.
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
4340.128
Nos.
10.00
43401.28
Sub-Total(A1)
43401.28
43401.28
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
15.245
bag
405.00
6174.23
Cement: CEM-I, 52.5-OPC
31.207
bag
440.00
13731.08
Sub-Total(A2)
19905.31
19905.31
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (FM=0.8)
5.623
cft
16.70
93.90
Sand (F.M.1.2)
123.141
cft
19.00
2339.68
Sand (F.M.2.2)
39.008
cft
53.80
2098.63
Sub-Total(A4)
4532.21
4532.21
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Manhole Cover-450mm D
3.000
no.
910.00
2730.00
RCC Tee
2.000
no.
450.00
900.00
Sub-Total(B1)
3630.00
3630.00
D1.Prop/Pipe/I-sec/Box
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo prop-use 8 times
56.046
No.
17.25
966.79
Sub-Total(D1)
966.79
966.79
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
9.288
sft
10.00
92.88
Mixer m/c hire charge
0.173
day
1200.00
207.60
Vibrator m/c hire charge
0.347
day
550.00
190.85
Fuel for mixer m/c, vibra
0.173
day
1275.00
220.58
Sub-Total(E1)
711.91
711.91
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Garjan wood use 8 times
4.887
cft
275.00
1343.93
Wood for Shutter use 8-ti
16.814
cft
68.75
1155.96
Sub-Total(F1)
2499.89
2499.89
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Sheet/ Plate-use 30 ti
285.833
kg
2.56
731.73
MS Rod 300 grade/ 40 grad
266.334
kg
65.00
17311.71
Sub-Total(F2)
18043.44
18043.44
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
21.657
No.
550.00
11911.35
Mason
7.013
No.
700.00
4909.10
Skilled Labour
5.488
No.
600.00
3292.80
Head Mason
1.205
No.
800.00
964.00
Sub-Total(L1)
21077.25
21077.25
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Breaking 20mm brick-chips
156.033
cft
9.70
1513.52
Wood shuttering i/c makin
257.810
sft
18.00
4640.58
Septic Tank-Fill,Clean
0.747
LS
1500.00
1120.50
Sub-Total(L2)
7274.60
7274.60
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making form water tight
257.810
sft
3.00
773.43
Sub-Total(L3)
773.43
773.43
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nail and wires, gazals
2.242
kg
70.00
156.94
Curing for 28 days
257.810
sft
4.58
1180.77
Sub-Total(M1)
1337.71
1337.71
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
4.125
No.
550.00
2268.75
Sub-Total(M2)
2268.75
2268.75
Total(1)
126422.57
Add over head on Total(1)
3.5 %
4424.79
Add Profit on Total(1)
10.0 %
12642.26
Total(2)
17067.05
Add VAT on Unit Price
5.5 %
993.32
Unit Price
18060.37
Say
18060
per each