BREAKDOWN OF UNIT PRICE
Item:267402. Septic Tank for 100 Users
Basis:1no.
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
7286.859
Nos.
10.00
72868.59
Sub-Total(A1)
72868.59
72868.59
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
25.978
bag
405.00
10521.09
Cement: CEM-I, 52.5-OPC
45.860
bag
440.00
20178.40
Sub-Total(A2)
30699.49
30699.49
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (FM=0.8)
8.297
cft
16.70
138.56
Sand (F.M.1.2)
203.524
cft
19.00
3866.96
Sand (F.M.2.2)
57.326
cft
53.80
3084.14
Sub-Total(A4)
7089.65
7089.65
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Manhole Cover-450mm D
3.000
no.
910.00
2730.00
RCC Tee
2.000
no.
450.00
900.00
Sub-Total(B1)
3630.00
3630.00
D1.Prop/Pipe/I-sec/Box
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo prop-use 8 times
82.835
No.
17.25
1428.90
Sub-Total(D1)
1428.90
1428.90
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
9.998
sft
10.00
99.98
Mixer m/c hire charge
0.255
day
1200.00
306.00
Vibrator m/c hire charge
0.510
day
550.00
280.50
Fuel for mixer m/c, vibra
0.255
day
1275.00
325.13
Sub-Total(E1)
1011.61
1011.61
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Garjan wood use 8 times
7.223
cft
275.00
1986.33
Wood for Shutter use 8-ti
24.850
cft
68.75
1708.44
Sub-Total(F1)
3694.76
3694.76
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Sheet/ Plate-use 30 ti
422.457
kg
2.56
1081.49
MS Rod 300 grade/ 40 grad
400.635
kg
65.00
26041.28
Sub-Total(F2)
27122.76
27122.76
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
36.317
No.
550.00
19974.35
Mason
11.021
No.
700.00
7714.70
Skilled Labour
9.214
No.
600.00
5528.40
Head Mason
1.832
No.
800.00
1465.60
Sub-Total(L1)
34683.05
34683.05
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Breaking 20mm brick-chips
229.202
cft
9.70
2223.26
Wood shuttering i/c makin
381.040
sft
18.00
6858.72
Septic Tank-Fill,Clean
0.853
LS
1500.00
1279.50
Sub-Total(L2)
10361.48
10361.48
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making form water tight
381.040
sft
3.00
1143.12
Sub-Total(L3)
1143.12
1143.12
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nail and wires, gazals
3.313
kg
70.00
231.91
Curing for 28 days
381.040
sft
4.58
1745.16
Sub-Total(M1)
1977.07
1977.07
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
6.499
No.
550.00
3574.45
Sub-Total(M2)
3574.45
3574.45
Total(1)
199284.94
Add over head on Total(1)
3.5 %
6974.97
Add Profit on Total(1)
10.0 %
19928.49
Total(2)
26903.47
Add VAT on Unit Price
5.5 %
1565.81
Unit Price
28469.28
Say
28469
per each