BREAKDOWN OF UNIT PRICE
Item:267401. Septic Tank for 200 Users
Basis:1no.
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
8867.488
Nos.
10.00
88674.88
Sub-Total(A1)
88674.88
88674.88
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
30.623
bag
405.00
12402.32
Cement: CEM-I, 52.5-OPC
64.892
bag
440.00
28552.48
Sub-Total(A2)
40954.80
40954.80
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (FM=0.8)
12.545
cft
16.70
209.50
Sand (F.M.1.2)
249.523
cft
19.00
4740.94
Sand (F.M.2.2)
81.115
cft
53.80
4363.99
Sub-Total(A4)
9314.43
9314.43
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Manhole Cover-450mm D
3.000
no.
910.00
2730.00
RCC Tee
2.000
no.
450.00
900.00
Sub-Total(B1)
3630.00
3630.00
D1.Prop/Pipe/I-sec/Box
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo prop-use 8 times
115.952
No.
17.25
2000.17
Sub-Total(D1)
2000.17
2000.17
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
14.880
sft
10.00
148.80
Mixer m/c hire charge
0.361
day
1200.00
433.20
Vibrator m/c hire charge
0.721
day
550.00
396.55
Fuel for mixer m/c, vibra
0.361
day
1275.00
460.28
Sub-Total(E1)
1438.83
1438.83
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Garjan wood use 8 times
10.111
cft
275.00
2780.53
Wood for Shutter use 8-ti
34.786
cft
68.75
2391.54
Sub-Total(F1)
5172.06
5172.06
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Sheet/ Plate-use 30 ti
591.356
kg
2.56
1513.87
MS Rod 300 grade/ 40 grad
549.909
kg
65.00
35744.09
Sub-Total(F2)
37257.96
37257.96
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
45.902
No.
550.00
25246.10
Mason
14.152
No.
700.00
9906.40
Skilled Labour
12.011
No.
600.00
7206.60
Head Mason
2.431
No.
800.00
1944.80
Sub-Total(L1)
44303.90
44303.90
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Breaking 20mm brick-chips
324.459
cft
9.70
3147.25
Wood shuttering i/c makin
533.380
sft
18.00
9600.84
Septic Tank-Fill,Clean
1.000
LS
1500.00
1500.00
Sub-Total(L2)
14248.09
14248.09
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making form water tight
533.380
sft
3.00
1600.14
Sub-Total(L3)
1600.14
1600.14
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nail and wires, gazals
4.638
kg
70.00
324.66
Curing for 28 days
533.380
sft
4.58
2442.88
Sub-Total(M1)
2767.54
2767.54
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
8.536
No.
550.00
4694.80
Sub-Total(M2)
4694.80
4694.80
Total(1)
256057.59
Add over head on Total(1)
3.5 %
8962.02
Add Profit on Total(1)
10.0 %
25605.76
Total(2)
34567.77
Add VAT on Unit Price
5.5 %
2011.88
Unit Price
36579.66
Say
36580
per each