BREAKDOWN OF UNIT PRICE
Item:267203. RCC Pit Cover-CI Cov-1100x1100x75
Basis:1no.
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
22.415
Nos.
10.00
224.15
Sub-Total(A1)
224.15
224.15
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.231
bag
405.00
93.56
Cement: CEM-I, 52.5-OPC
0.527
bag
440.00
231.88
Sub-Total(A2)
325.44
325.44
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
1.428
cft
19.00
27.13
Sand (F.M.2.2)
0.659
cft
53.80
35.45
Sub-Total(A4)
62.59
62.59
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Manhole Cover-450mm D
1.000
no.
910.00
910.00
Sub-Total(B1)
910.00
910.00
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c hire charge
0.003
day
1200.00
3.60
Vibrator m/c hire charge
0.006
day
550.00
3.30
Fuel for mixer m/c, vibra
0.003
day
1275.00
3.83
Sub-Total(E1)
10.73
10.73
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Rod 300 grade/ 40 grad
6.515
kg
65.00
423.48
Sub-Total(F2)
423.48
423.48
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.351
No.
550.00
193.05
Mason
0.198
No.
700.00
138.60
Skilled Labour
0.015
No.
600.00
9.00
Head Mason
0.041
No.
800.00
32.80
Sub-Total(L1)
373.45
373.45
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Breaking 20mm brick-chips
2.637
cft
9.70
25.58
Sub-Total(L2)
25.58
25.58
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.092
No.
550.00
50.60
Sub-Total(M2)
50.60
50.60
Total(1)
2406.00
Add over head on Total(1)
3.5 %
84.21
Add Profit on Total(1)
10.0 %
240.60
Total(2)
324.81
Add VAT on Unit Price
5.5 %
18.90
Unit Price
343.71
Say
344
per each