BREAKDOWN OF UNIT PRICE
Item:267201. RCC Pit Cover-CI Cover-950x950x75
Basis:1no.
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
15.836
Nos.
10.00
158.36
Sub-Total(A1)
158.36
158.36
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.198
bag
405.00
80.19
Cement: CEM-I, 52.5-OPC
0.373
bag
440.00
164.12
Sub-Total(A2)
244.31
244.31
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
1.127
cft
19.00
21.41
Sand (F.M.2.2)
0.466
cft
53.80
25.07
Sub-Total(A4)
46.48
46.48
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Manhole Cover-450mm D
1.000
no.
910.00
910.00
Sub-Total(B1)
910.00
910.00
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c hire charge
0.002
day
1200.00
2.40
Vibrator m/c hire charge
0.004
day
550.00
2.20
Fuel for mixer m/c, vibra
0.002
day
1275.00
2.55
Sub-Total(E1)
7.15
7.15
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Rod 300 grade/ 40 grad
4.601
kg
65.00
299.07
Sub-Total(F2)
299.07
299.07
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.307
No.
550.00
168.85
Mason
0.169
No.
700.00
118.30
Skilled Labour
0.011
No.
600.00
6.60
Head Mason
0.035
No.
800.00
28.00
Sub-Total(L1)
321.75
321.75
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Breaking 20mm brick-chips
1.863
cft
9.70
18.07
Sub-Total(L2)
18.07
18.07
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.076
No.
550.00
41.80
Sub-Total(M2)
41.80
41.80
Total(1)
2046.99
Add over head on Total(1)
3.5 %
71.64
Add Profit on Total(1)
10.0 %
204.70
Total(2)
276.34
Add VAT on Unit Price
5.5 %
16.08
Unit Price
292.43
Say
292
per each