BREAKDOWN OF UNIT PRICE
Item:2668. Punching/Cutting Hole RCC Floor
Basis:1no.
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.100
No.
550.00
55.00
Skilled Labour
0.100
No.
600.00
60.00
Sub-Total(L1)
115.00
115.00
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Punching Hole-Good damage
1.000
no.
25.00
25.00
Sub-Total(L2)
25.00
25.00
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.045
No.
550.00
24.75
Sub-Total(M2)
24.75
24.75
Total(1)
164.75
Add over head on Total(1)
3.5 %
5.77
Add Profit on Total(1)
10.0 %
16.48
Total(2)
22.24
Add VAT on Unit Price
5.5 %
1.29
Unit Price
23.54
Say
24
per each