BREAKDOWN OF UNIT PRICE
Item:265604. uPVC Cleanout-P/ S Trap-100mm dia
Basis:1no.
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Cleanout-P/STrap-100
1.000
no.
250.00
250.00
Sub-Total(B1)
250.00
250.00
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Solvent Cement
10.000
ml
0.85
8.50
Sub-Total(B2)
8.50
8.50
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.095
No.
550.00
52.25
Skilled Labour
0.050
No.
600.00
30.00
Plumber
0.025
No.
700.00
17.50
Sub-Total(L1)
99.75
99.75
Total(1)
358.25
Add over head on Total(1)
3.5 %
12.54
Add Profit on Total(1)
10.0 %
35.83
Total(2)
48.36
Add VAT on Unit Price
5.5 %
2.81
Unit Price
51.18
Say
51
per each