BREAKDOWN OF UNIT PRICE
Item:265601. uPVC Cleanout-Y/ T-Y-50mm dia
Basis:1no.
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Cleanout-Y/T-Y-50mm
1.000
no.
180.00
180.00
Sub-Total(B1)
180.00
180.00
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Solvent Cement
10.000
ml
0.85
8.50
Sub-Total(B2)
8.50
8.50
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.095
No.
550.00
52.25
Skilled Labour
0.050
No.
600.00
30.00
Plumber
0.025
No.
700.00
17.50
Sub-Total(L1)
99.75
99.75
Total(1)
288.25
Add over head on Total(1)
3.5 %
10.09
Add Profit on Total(1)
10.0 %
28.83
Total(2)
38.91
Add VAT on Unit Price
5.5 %
2.26
Unit Price
41.18
Say
41
per each