BREAKDOWN OF UNIT PRICE
Item:264803. RCC Pipoe-300mm dia t=50mm
Basis:18rft
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.400
bag
405.00
162.00
Sub-Total(A2)
162.00
29.53
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
1.000
cft
19.00
19.00
Sub-Total(A4)
19.00
3.46
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe-300D L=1830 t=50
3.000
no.
3210.00
9630.00
Sub-Total(B1)
9630.00
1755.34
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hem
23.573
sft
2.97
70.01
Sub-Total(B2)
70.01
12.76
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.000
No.
550.00
1100.00
Skilled Labour
0.500
No.
600.00
300.00
Plumber
0.500
No.
700.00
350.00
Sub-Total(L1)
1750.00
318.99
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavation (underground)
175.160
cft
3.88
679.62
Sand (FM 0.8) bedding-UG
21.960
cft
19.00
417.24
Sub-Total(L2)
1096.86
199.93
Total(1)
2320.01
Add over head on Total(1)
3.5 %
81.20
Add Profit on Total(1)
10.0 %
232.00
Total(2)
313.20
Add VAT on Unit Price
5.5 %
18.23
Unit Price
331.43
Say
331
per metr