BREAKDOWN OF UNIT PRICE
Item:264801. RCC Pipoe-150mm dia t=40mm
Basis:18rft
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.200
bag
405.00
81.00
Sub-Total(A2)
81.00
14.76
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
0.520
cft
19.00
9.88
Sub-Total(A4)
9.88
1.80
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe-150D L=1830 t=40
3.000
no.
1160.00
3480.00
Sub-Total(B1)
3480.00
634.33
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hem
14.531
sft
2.97
43.16
Sub-Total(B2)
43.16
7.87
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.500
No.
550.00
275.00
Skilled Labour
0.500
No.
600.00
300.00
Plumber
0.250
No.
700.00
175.00
Sub-Total(L1)
750.00
136.71
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavation (underground)
72.750
cft
3.88
282.27
Sand (FM 0.8) bedding-UG
12.780
cft
19.00
242.82
Sub-Total(L2)
525.09
95.71
Total(1)
891.18
Add over head on Total(1)
3.5 %
31.19
Add Profit on Total(1)
10.0 %
89.12
Total(2)
120.31
Add VAT on Unit Price
5.5 %
7.00
Unit Price
127.31
Say
127
per metr