BREAKDOWN OF UNIT PRICE
Item:264403. uPVC UG Pipe-D=250mm t=6.6-7.6mm
Basis:20rft
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe-D=250-t=6.6-7.6
20.000
rft
646.00
12920.00
Sub-Total(B1)
12920.00
2119.53
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Solvent Cement
330.000
ml
0.85
280.50
Sub-Total(B2)
280.50
46.02
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.500
No.
550.00
275.00
Skilled Labour
0.500
No.
600.00
300.00
Plumber
0.250
No.
700.00
175.00
Sub-Total(L1)
750.00
123.04
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavation (underground)
87.500
cft
3.88
339.50
Sand (FM 0.8) bedding-UG
52.500
cft
19.00
997.50
Sub-Total(L2)
1337.00
219.33
Total(1)
2507.91
Add over head on Total(1)
3.5 %
87.78
Add Profit on Total(1)
10.0 %
250.79
Total(2)
338.57
Add VAT on Unit Price
5.5 %
19.71
Unit Price
358.27
Say
358
per metr