Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:264402. uPVC UG Pipe-D=200mm t=5.3-7.8mm
Basis:20rft
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe-D=200-t=5.3-7.8
20.000
rft
402.00
8040.00
Sub-Total(B1)
8040.00
1318.96
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Solvent Cement
50.000
ml
0.85
42.50
Sub-Total(B2)
42.50
6.97
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.500
No.
550.00
275.00
Skilled Labour
0.500
No.
600.00
300.00
Plumber
0.250
No.
700.00
175.00
Sub-Total(L1)
750.00
123.04
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavation (underground)
87.500
cft
3.88
339.50
Sand (FM 0.8) bedding-UG
67.500
cft
19.00
1282.50
Sub-Total(L2)
1622.00
266.09
Total(1)
1715.06
Add over head on Total(1)
3.5 %
60.03
Add Profit on Total(1)
10.0 %
171.51
Total(2)
231.53
Add VAT on Unit Price
5.5 %
13.48
Unit Price
245.01
Say
245
per metr