BREAKDOWN OF UNIT PRICE
Item:264401. uPVC UG Pipe-D=150mm t=4.5-6.6mm
Basis:20rft
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC Pipe-D=150-t=4.5-5.2
20.000
rft
263.00
5260.00
Sub-Total(B1)
5260.00
862.90
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Solvent Cement
50.000
ml
0.85
42.50
Sub-Total(B2)
42.50
6.97
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.500
No.
550.00
275.00
Skilled Labour
0.500
No.
600.00
300.00
Plumber
0.250
No.
700.00
175.00
Sub-Total(L1)
750.00
123.04
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavation (underground)
62.500
cft
3.88
242.50
Sand (FM 0.8) bedding-UG
38.800
cft
19.00
737.20
Sub-Total(L2)
979.70
160.72
Total(1)
1153.63
Add over head on Total(1)
3.5 %
40.38
Add Profit on Total(1)
10.0 %
115.36
Total(2)
155.74
Add VAT on Unit Price
5.5 %
9.06
Unit Price
164.80
Say
165
per metr