BREAKDOWN OF UNIT PRICE
Item:261901. Double Coated Mirror-5mm-Local
Basis:3sft
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mirror-5mm-Local
2.906
sft
98.01
284.82
Sub-Total(B1)
284.82
1054.98
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastic Clip
4.000
no.
11.00
44.00
Rowel Plug-screw-50mm
4.000
nos
9.00
36.00
Sub-Total(B2)
80.00
296.32
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.200
No.
550.00
110.00
Skilled Labour
0.100
No.
600.00
60.00
Plumber
0.050
No.
700.00
35.00
Sub-Total(L1)
205.00
759.33
Total(1)
2110.64
Add over head on Total(1)
3.5 %
73.87
Add Profit on Total(1)
10.0 %
211.06
Total(2)
284.94
Add VAT on Unit Price
5.5 %
16.58
Unit Price
301.52
Say
302
per sqm