BREAKDOWN OF UNIT PRICE
Item:261801. Doubl Bowl SS Sink-1160x500-Stand
Basis:1no.
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.022
bag
405.00
8.91
Sub-Total(A2)
8.91
8.91
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
0.120
cft
19.00
2.28
Sub-Total(A4)
2.28
2.28
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Doubl SS Sink-1160x500-St
1.000
no.
5000.00
5000.00
Sub-Total(B1)
5000.00
5000.00
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Grating with Brass coupli
2.000
no.
300.00
600.00
PVC Waste Pipe-32mm
1.000
no.
360.00
360.00
C.I. Bracket
3.000
pair
150.00
450.00
CP Chain with rubber plug
1.000
no.
80.00
80.00
Sub-Total(B2)
1490.00
1490.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour
0.400
No.
600.00
240.00
Plumber
0.250
No.
700.00
175.00
Sub-Total(L1)
415.00
415.00
Total(1)
6916.19
Add over head on Total(1)
3.5 %
242.07
Add Profit on Total(1)
10.0 %
691.62
Total(2)
933.69
Add VAT on Unit Price
5.5 %
54.34
Unit Price
988.03
Say
988
per each