BREAKDOWN OF UNIT PRICE
Item:261312. Wash Basin Padestal-648x488-20kg
Basis:1no.
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.010
bag
405.00
4.05
Sub-Total(A2)
4.05
4.05
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
0.050
cft
19.00
0.95
Sub-Total(A4)
0.95
0.95
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Basin Padestal-648x488-20
1.000
no.
2975.00
2975.00
Sub-Total(B1)
2975.00
2975.00
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Grating with Brass coupli
1.000
no.
300.00
300.00
PVC Waste Pipe-32mm
1.000
no.
360.00
360.00
C.I. Bracket
1.000
pair
150.00
150.00
CP Chain with rubber plug
1.000
no.
80.00
80.00
Sub-Total(B2)
890.00
890.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.400
No.
550.00
220.00
Skilled Labour
0.200
No.
600.00
120.00
Plumber
0.150
No.
700.00
105.00
Sub-Total(L1)
445.00
445.00
Total(1)
4315.00
Add over head on Total(1)
3.5 %
151.03
Add Profit on Total(1)
10.0 %
431.50
Total(2)
582.53
Add VAT on Unit Price
5.5 %
33.90
Unit Price
616.43
Say
616
per each