BREAKDOWN OF UNIT PRICE
Item:261208. Wash Basin Table Top-450x450-10
Basis:1no.
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.010
bag
405.00
4.05
Sub-Total(A2)
4.05
4.05
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
0.050
cft
19.00
0.95
Sub-Total(A4)
0.95
0.95
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wash Basin-TT-450x450-10
1.000
no.
3760.00
3760.00
Sub-Total(B1)
3760.00
3760.00
B2.Sanitary Accessories
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Grating with Brass coupli
1.000
no.
300.00
300.00
PVC Waste Pipe-32mm
1.000
no.
360.00
360.00
C.I. Bracket
1.000
pair
150.00
150.00
CP Chain with rubber plug
1.000
no.
80.00
80.00
Sub-Total(B2)
890.00
890.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.500
No.
550.00
275.00
Skilled Labour
0.500
No.
600.00
300.00
Plumber
0.150
No.
700.00
105.00
Sub-Total(L1)
680.00
680.00
Total(1)
5335.00
Add over head on Total(1)
3.5 %
186.73
Add Profit on Total(1)
10.0 %
533.50
Total(2)
720.23
Add VAT on Unit Price
5.5 %
41.92
Unit Price
762.14
Say
762
per each