BREAKDOWN OF UNIT PRICE |
Item:261205. Wash Basin under countr-570x420-7 |
Basis:1no. | |
A2.Cement |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement: CEM-II/A,52.5-PCC | 0.010 | bag |
405.00 | |
|
|
Sub-Total(A2) |
4.05
|
4.05
|
A4.Earth/ Sand |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand (F.M.1.2) | 0.050 | cft |
19.00 | |
|
|
Sub-Total(A4) |
0.95
|
0.95
|
B1.Sanitary- Water Supp |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Wash Basin-UC-570x420-7.5 | 1.000 | no. |
1905.00 | |
|
|
Sub-Total(B1) |
1905.00
|
1905.00
|
B2.Sanitary Accessories |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Grating with Brass coupli | 1.000 | no. |
300.00 | |
|
PVC Waste Pipe-32mm | 1.000 | no. |
360.00 | |
|
C.I. Bracket | 1.000 | pair |
150.00 | |
|
CP Chain with rubber plug | 1.000 | no. |
80.00 | |
|
|
Sub-Total(B2) |
890.00
|
890.00
|
L1.Labour-Civil |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour | 0.500 | No. |
550.00 | |
|
Skilled Labour | 0.500 | No. |
600.00 | |
|
Plumber | 0.150 | No. |
700.00 | |
|
|
Sub-Total(L1) |
680.00
|
680.00
|
|
|
|
Total(1) |
|
3480.00 |
|
Add over head on Total(1)
|
3.5 % |
121.80 |
|
Add Profit on Total(1) |
10.0 % |
348.00
|
|
|
|
Total(2) |
|
469.80 |
|
Add VAT on Unit Price |
5.5 % |
27.34 |
|
|
|
Unit Price |
|
497.14
|
|
|
|
Say |
497 |
per each |