BREAKDOWN OF UNIT PRICE
Item:2606. Flat or Squating Urinal-9.5 kg
Basis:1no.
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.200
bag
405.00
81.00
Sub-Total(A2)
81.00
81.00
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
0.100
cft
19.00
1.90
Sub-Total(A4)
1.90
1.90
B1.Sanitary- Water Supp
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Flat/ Squating Urinal-9.5
1.000
no.
2050.00
2050.00
Sub-Total(B1)
2050.00
2050.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.500
No.
550.00
275.00
Skilled Labour
0.250
No.
600.00
150.00
Plumber
0.200
No.
700.00
140.00
Sub-Total(L1)
565.00
565.00
Total(1)
2697.90
Add over head on Total(1)
3.5 %
94.43
Add Profit on Total(1)
10.0 %
269.79
Total(2)
364.22
Add VAT on Unit Price
5.5 %
21.20
Unit Price
385.41
Say
385
per each