BREAKDOWN OF UNIT PRICE
Item:241902. Prime Coat @1.2L/m2 by Mech Distr
Basis:100sft
A3.Stone/ Mosaic/ Admix
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bitumen (60/70 grade)
7.438
kg
56.00
416.53
Kerosene
3.750
litr
68.00
255.00
Sub-Total(A3)
671.53
72.28
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hire Charge-Distributor
0.003
day
5500.00
16.50
Sub-Total(E1)
16.50
1.78
E2.Equipment-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel
0.030
litr
68.00
2.04
Lubricants
0.003
litr
220.00
0.66
Sub-Total(E2)
2.70
0.29
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.120
No.
550.00
66.00
Mason
0.002
No.
700.00
1.40
Skilled Labour
0.020
No.
600.00
12.00
Sub-Total(L1)
79.40
8.55
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fire wood
0.333
mnds
220.00
73.26
Sub-Total(M1)
73.26
7.89
Total(1)
90.78
Add over head on Total(1)
3.5 %
3.18
Add Profit on Total(1)
10.0 %
9.08
Total(2)
103.04
Add VAT on Unit Price
7.5 %
8.35
Unit Price
111.39
Say
111
per sqm