BREAKDOWN OF UNIT PRICE
Item:2417. Tack Coat @ 750 kg per 10 sqm
Basis:100sft
A3.Stone/ Mosaic/ Admix
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bitumen (60/70 grade)
7.029
kg
56.00
393.62
Sub-Total(A3)
393.62
42.37
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.280
No.
550.00
154.00
Mason
0.004
No.
700.00
2.80
Skilled Labour
0.040
No.
600.00
24.00
Sub-Total(L1)
180.80
19.46
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fire wood
0.200
mnds
220.00
44.00
Sub-Total(M1)
44.00
4.74
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
0.100
LS
550.00
55.00
Sub-Total(M2)
55.00
5.92
Total(1)
72.49
Add over head on Total(1)
3.5 %
2.54
Add Profit on Total(1)
10.0 %
7.25
Total(2)
82.27
Add VAT on Unit Price
7.5 %
6.67
Unit Price
88.94
Say
89
per sqm