BREAKDOWN OF UNIT PRICE
Item:240102. Earthwork Road Embankmen 1.5-2.5m
Basis:1000cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
9.200
No.
550.00
5060.00
Mason
0.250
No.
700.00
175.00
Sub-Total(L1)
5235.00
184.87
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
0.100
LS
550.00
55.00
Sub-Total(M2)
55.00
1.94
Total(1)
186.82
Add over head on Total(1)
3.5 %
6.54
Add Profit on Total(1)
10.0 %
18.68
Total(2)
212.04
Add VAT on Unit Price
7.5 %
17.19
Unit Price
229.23
Say
229
per cum