BREAKDOWN OF UNIT PRICE
Item:240101. Earthwork Road Embankmn upto 1.5m
Basis:1000cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
8.000
No.
550.00
4400.00
Mason
0.250
No.
700.00
175.00
Sub-Total(L1)
4575.00
161.57
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
0.100
LS
550.00
55.00
Sub-Total(M2)
55.00
1.94
Total(1)
163.51
Add over head on Total(1)
3.5 %
5.72
Add Profit on Total(1)
10.0 %
16.35
Total(2)
185.58
Add VAT on Unit Price
7.5 %
15.05
Unit Price
200.63
Say
201
per cum