BREAKDOWN OF UNIT PRICE
Item:222403. RCC Pipe-900mm dia
Basis:24rft
B8.RCC Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe-900mm dia-6 ft
4.000
each
15510.00
62040.00
RCC Pipe Socket-900mm
3.000
no.
400.00
1200.00
Sub-Total(B8)
63240.00
8645.44
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hire charge of truck
1.000
trip
2300.00
2300.00
Sub-Total(E1)
2300.00
314.43
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
4.000
No.
550.00
2200.00
Mason
0.500
No.
700.00
350.00
Skilled Labour
2.000
No.
600.00
1200.00
Sub-Total(L1)
3750.00
512.66
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement Concrete(1:3:6)
2.970
cft
178.37
529.76
Sub-Total(L3)
529.76
72.42
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
2.083
No.
550.00
1145.65
Sub-Total(M2)
1145.65
156.62
Total(1)
9701.56
Add over head on Total(1)
3.5 %
339.55
Add Profit on Total(1)
10.0 %
970.16
Total(2)
1309.71
Add VAT on Unit Price
5.5 %
76.23
Unit Price
1385.94
Say
1386
per metr