BREAKDOWN OF UNIT PRICE
Item:2221. Glass Brick (190) in round stair
Basis:6sft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glass brick-190x190
16.800
nos
370.00
6216.00
Sub-Total(A1)
6216.00
10705.44
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
White Cement
10.000
kg
27.00
270.00
Sub-Total(A2)
270.00
465.00
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
6.250
sft
10.00
62.50
Sub-Total(E1)
62.50
107.64
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Rod 300 grade/ 40 grad
4.546
kg
65.00
295.49
Sub-Total(F2)
295.49
508.90
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glass brick work
16.000
nos
52.50
840.00
Sub-Total(L2)
840.00
1446.68
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.125
No.
550.00
68.75
Sub-Total(M2)
68.75
118.40
Total(1)
13352.08
Add over head on Total(1)
3.5 %
467.32
Add Profit on Total(1)
10.0 %
1335.21
Total(2)
1802.53
Add VAT on Unit Price
5.5 %
104.91
Unit Price
1907.44
Say
1907
per sqm