Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:2215. uPVC door, window, partion frame
Basis:17rft
C2.Alum/ PVC Accessoris
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Clamp-200
6.000
nos
11.00
66.00
Welding-uPVC Partition
1.000
LS
105.00
105.00
Sub-Total(C2)
171.00
34.00
C3.Plastic Door/Win/Par
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
uPVC partion frame
17.000
rft
67.00
1139.00
uPVC Partion frame reinfo
14.000
rft
31.00
434.00
Sub-Total(C3)
1573.00
312.79
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Carpenter
1.000
No.
700.00
700.00
Sub-Total(L1)
700.00
139.19
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.078
No.
550.00
42.90
Sub-Total(M2)
42.90
8.53
Total(1)
494.52
Add over head on Total(1)
3.5 %
17.31
Add Profit on Total(1)
10.0 %
49.45
Total(2)
66.76
Add VAT on Unit Price
5.5 %
3.89
Unit Price
70.65
Say
71
per metr