Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:2204. Tempered Clear Glass Door-10mm
Basis:21sft
C2.Alum/ PVC Accessoris
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Floor Mountain Auto Closu
1.000
set
6200.00
6200.00
Clamping Device-Top/Bot
2.000
Nos.
1202.00
2404.00
Glass Door Locking Device
1.000
set
2800.00
2800.00
Glass DrTop Hinge-Pivotal
1.000
set
1250.00
1250.00
Glass Door Handle
1.000
set
2800.00
2800.00
Sub-Total(C2)
15454.00
7921.28
C3.Plastic Door/Win/Par
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glass-10mm tempered
21.630
sft
390.00
8435.70
Sub-Total(C3)
8435.70
4323.90
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
8.594
sft
10.00
85.94
Sub-Total(E1)
85.94
44.05
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Alum.Skilled Technicians
0.500
No.
1200.00
600.00
Alum.Semi-skill Techn
0.500
No.
800.00
400.00
Sub-Total(L1)
1000.00
512.57
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.313
No.
550.00
172.15
Sub-Total(M2)
172.15
88.24
Total(1)
12890.04
Add over head on Total(1)
3.5 %
451.15
Add Profit on Total(1)
10.0 %
1289.00
Total(2)
1740.16
Add VAT on Unit Price
5.5 %
101.28
Unit Price
1841.43
Say
1841
per sqm