BREAKDOWN OF UNIT PRICE
Item:2101. MS Grill Fencing-FI Bar 31x6mm
Basis:27sft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Workshop Charge
4379.090
perc
0.05
218.95
Sub-Total(E1)
218.95
87.35
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Flat (FI) Bar
36.320
kg
70.00
2542.40
Sub-Total(F2)
2542.40
1014.32
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
1.000
No.
550.00
550.00
Mason
0.500
No.
700.00
350.00
Helper
1.250
No.
550.00
687.50
Welder/ Fabricator
0.750
No.
700.00
525.00
Sub-Total(L1)
2112.50
842.81
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making Hole-MS Gate
4.000
Nos.
22.92
91.68
Sub-Total(L2)
91.68
36.58
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC (1:2:4)
0.130
cft
204.00
26.52
Sub-Total(L3)
26.52
10.58
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Rod (Electrode)
15.000
Nos
10.00
150.00
Sub-Total(M1)
150.00
59.84
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.364
No.
550.00
200.20
Sub-Total(M2)
200.20
79.87
Total(1)
2131.36
Add over head on Total(1)
3.5 %
74.60
Add Profit on Total(1)
10.0 %
213.14
Total(2)
287.73
Add VAT on Unit Price
5.5 %
16.75
Unit Price
304.48
Say
304
per sqm