BREAKDOWN OF UNIT PRICE
Item:201805. Stair Step Nosing-SSAngl-38x38x6
Basis:35rft
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Flat (FI) Bar
1.143
kg
70.00
80.01
SS Angle-38x38x6mm
36.750
rft
310.00
11392.50
Sub-Total(F2)
11472.51
1075.47
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.500
No.
550.00
275.00
Mason
0.500
No.
700.00
350.00
Skilled Labour
0.500
No.
600.00
300.00
Sub-Total(L1)
925.00
86.71
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Angle Cutting-Nosing
10.000
Nos.
10.00
100.00
FI Bar Welding-Nosing
30.000
Nos.
10.00
300.00
Sub-Total(L2)
400.00
37.50
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC (1:2:4)
0.140
cft
204.00
28.56
Sub-Total(L3)
28.56
2.68
Total(1)
1202.35
Add over head on Total(1)
3.5 %
42.08
Add Profit on Total(1)
10.0 %
120.24
Total(2)
162.32
Add VAT on Unit Price
5.5 %
9.45
Unit Price
171.76
Say
172
per metr