Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:201702. MS Box Ver Railing-75x75x5 box
Basis:46sft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Workshop Charge
20309.240
perc
0.05
1015.46
Sub-Total(E1)
1015.46
240.23
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Plate-250 MPa
2.391
kg
77.00
184.11
MS Hollow box
190.222
kg
77.00
14647.09
Sub-Total(F2)
14831.20
3508.64
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.500
No.
550.00
1375.00
Mason
0.250
No.
700.00
175.00
Helper
3.000
No.
550.00
1650.00
Welder/ Fabricator
1.250
No.
700.00
875.00
Sub-Total(L1)
4075.00
964.03
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Rowel Bolt
20.000
Nos
57.00
1140.00
Welding Rod (Electrode)
120.000
Nos
10.00
1200.00
Sub-Total(M1)
2340.00
553.58
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.445
No.
550.00
244.75
Sub-Total(M2)
244.75
57.90
Total(1)
5324.37
Add over head on Total(1)
3.5 %
186.35
Add Profit on Total(1)
10.0 %
532.44
Total(2)
718.79
Add VAT on Unit Price
5.5 %
41.83
Unit Price
760.62
Say
761
per sqm