BREAKDOWN OF UNIT PRICE
Item:201503. TempGlssVerRail-10mm-SS -U Channl
Basis:46sft
B7.GI/ SS Pipe/ Fitting
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Pipe-D=62mm, t=2mm
14.180
rft
285.00
4041.30
SS Royal bolt Cap
20.000
Nos
30.00
600.00
SS Plate-100x100x6
5.000
nos.
200.00
1000.00
SS End cap-62mm
2.000
nos.
70.00
140.00
SS Holder knob
16.000
nos.
225.00
3600.00
SS Pipe-50mm D t=2 Post
5.000
nos.
1800.00
9000.00
Sub-Total(B7)
18381.30
4348.49
C3.Plastic Door/Win/Par
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glass-10mm tempered
37.230
sft
390.00
14519.70
Sub-Total(C3)
14519.70
3434.95
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Railing workshop charg
0.867
LS
1500.00
1300.50
Sub-Total(E1)
1300.50
307.66
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.000
No.
550.00
1100.00
Helper
1.500
No.
550.00
825.00
Alum.Skilled Technicians
0.500
No.
1200.00
600.00
Alum.Semi-skill Techn
1.000
No.
800.00
800.00
Welder/ Fabricator
0.500
No.
700.00
350.00
Sub-Total(L1)
3675.00
869.40
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cutting Glass hole
20.000
nos
31.00
620.00
Sub-Total(L2)
620.00
146.67
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Rowel Bolt
20.000
Nos
57.00
1140.00
Welding Rod (Electrode)
100.000
Nos
10.00
1000.00
SS Railing Poilising
36890.700
perc
0.10
3689.07
Sub-Total(M1)
5829.07
1378.99
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.636
No.
550.00
349.80
Sub-Total(M2)
349.80
82.75
Total(1)
10568.92
Add over head on Total(1)
3.5 %
369.91
Add Profit on Total(1)
10.0 %
1056.89
Total(2)
1426.80
Add VAT on Unit Price
5.5 %
83.04
Unit Price
1509.85
Say
1510
per sqm