BREAKDOWN OF UNIT PRICE
Item:200501. MS Box Stair Railing-38x6 FI Bar
Basis:32sft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Workshop Charge
10533.940
perc
0.05
526.70
Sub-Total(E1)
526.70
178.90
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Flat (FI) Bar
32.931
kg
70.00
2305.17
MS Plate-250 MPa
0.404
kg
77.00
31.11
MS Hollow box
39.492
kg
77.00
3040.88
Sub-Total(F2)
5377.16
1826.44
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.500
No.
550.00
1375.00
Mason
0.250
No.
700.00
175.00
Helper
2.500
No.
550.00
1375.00
Welder/ Fabricator
1.250
No.
700.00
875.00
Sub-Total(L1)
3800.00
1290.73
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Rowel Bolt
12.000
Nos
57.00
684.00
Welding Rod (Electrode)
140.000
Nos
10.00
1400.00
Sub-Total(M1)
2084.00
707.86
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.818
No.
550.00
449.90
Sub-Total(M2)
449.90
152.82
Total(1)
4156.74
Add over head on Total(1)
3.5 %
145.49
Add Profit on Total(1)
10.0 %
415.67
Total(2)
561.16
Add VAT on Unit Price
5.5 %
32.66
Unit Price
593.82
Say
594
per sqm