Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:200402. GI Pipe Stair Railing-50mm dia
Basis:30sft
B7.GI/ SS Pipe/ Fitting
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
G.I. Pipe-12 mm dia
70.000
rft
61.00
4270.00
G.I. Pipe-50 mm dia
10.500
rft
215.00
2257.50
Sub-Total(B7)
6527.50
2342.07
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Workshop Charge
9712.720
perc
0.05
485.64
Sub-Total(E1)
485.64
174.25
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Plate-250 MPa
2.731
kg
77.00
210.29
Sub-Total(F2)
210.29
75.45
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.000
No.
550.00
1100.00
Mason
0.250
No.
700.00
175.00
Helper
1.500
No.
550.00
825.00
Welder/ Fabricator
0.750
No.
700.00
525.00
Sub-Total(L1)
2625.00
941.85
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cutting Groove-50x50x150
20.000
No.
18.33
366.60
Sub-Total(L2)
366.60
131.54
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC (1:2:4)
0.280
cft
204.00
57.12
Sub-Total(L3)
57.12
20.49
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Rod (Electrode)
80.000
Nos
10.00
800.00
Sub-Total(M1)
800.00
287.04
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.818
No.
550.00
449.90
Sub-Total(M2)
449.90
161.42
Total(1)
4134.11
Add over head on Total(1)
3.5 %
144.69
Add Profit on Total(1)
10.0 %
413.41
Total(2)
558.10
Add VAT on Unit Price
5.5 %
32.48
Unit Price
590.59
Say
591
per sqm