BREAKDOWN OF UNIT PRICE
Item:200301. GI Pipe Stair Railing - 150x62
Basis:28sft
B7.GI/ SS Pipe/ Fitting
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
G.I. Pipe-12 mm dia
35.000
rft
61.00
2135.00
Sub-Total(B7)
2135.00
832.65
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Workshop Charge
4817.100
perc
0.05
240.86
Sub-Total(E1)
240.86
93.93
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Flat (FI) Bar
5.948
kg
70.00
416.36
MS Plate-250 MPa
1.343
kg
77.00
103.41
Sub-Total(F2)
519.77
202.71
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
1.250
No.
550.00
687.50
Mason
0.250
No.
700.00
175.00
Helper
1.250
No.
550.00
687.50
Welder/ Fabricator
0.750
No.
700.00
525.00
Sub-Total(L1)
2075.00
809.25
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cutting Groove-50x50x150
10.000
No.
18.33
183.30
Sub-Total(L2)
183.30
71.49
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC (1:2:4)
0.140
cft
204.00
28.56
Sub-Total(L3)
28.56
11.14
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Rod (Electrode)
40.000
Nos
10.00
400.00
Sub-Total(M1)
400.00
156.00
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.818
No.
550.00
449.90
Sub-Total(M2)
449.90
175.46
Total(1)
2352.63
Add over head on Total(1)
3.5 %
82.34
Add Profit on Total(1)
10.0 %
235.26
Total(2)
317.61
Add VAT on Unit Price
5.5 %
18.48
Unit Price
336.09
Say
336
per sqm