BREAKDOWN OF UNIT PRICE
Item:1701022. Waterproofing roof with fibermesh
Basis:100sft
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
FiberElastromatric Liquid
10.000
litr
628.00
6280.00
Sub-Total(A2)
6280.00
675.98
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour
1.500
No.
600.00
900.00
Skilled Technician
0.500
no
1200.00
600.00
Sub-Total(L1)
1500.00
161.46
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glass fiber mesh(10x10mm)
105.000
sft
7.50
787.50
Sub-Total(M1)
787.50
84.77
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
1.000
No.
550.00
550.00
Sub-Total(M2)
550.00
59.20
Total(1)
981.41
Add over head on Total(1)
3.5 %
34.35
Add Profit on Total(1)
10.0 %
98.14
Total(2)
132.49
Add VAT on Unit Price
5.5 %
7.71
Unit Price
140.20
Say
140
per sqm