BREAKDOWN OF UNIT PRICE
Item:1701021. Waterproofing roof without mesh
Basis:100sft
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
FiberElastromatric Liquid
10.000
litr
628.00
6280.00
Sub-Total(A2)
6280.00
675.98
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour
1.250
No.
600.00
750.00
Skilled Technician
0.500
no
1200.00
600.00
Sub-Total(L1)
1350.00
145.31
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
1.000
No.
550.00
550.00
Sub-Total(M2)
550.00
59.20
Total(1)
880.50
Add over head on Total(1)
3.5 %
30.82
Add Profit on Total(1)
10.0 %
88.05
Total(2)
118.87
Add VAT on Unit Price
5.5 %
6.92
Unit Price
125.79
Say
126
per sqm