BREAKDOWN OF UNIT PRICE
Item:161002. Wood Varnising with Egg-shell
Basis:100sft
F5.Polish
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand paper
4.000
Nos.
16.00
64.00
Markin cloth
0.500
yard
11.50
5.75
Varnish Egg-shell
1.330
litr
280.00
372.40
Wood Varnish Thinner
0.340
litr
131.00
44.54
Sub-Total(F5)
486.69
52.39
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.750
No.
550.00
412.50
Painter
0.750
No.
700.00
525.00
Sub-Total(L1)
937.50
100.91
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.300
No.
550.00
165.00
Sub-Total(M2)
165.00
17.76
Total(1)
171.06
Add over head on Total(1)
3.5 %
5.99
Add Profit on Total(1)
10.0 %
17.11
Total(2)
23.09
Add VAT on Unit Price
5.5 %
1.34
Unit Price
24.44
Say
24
per sqm