Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:1519. Embed Broken Glass into Plaster
Basis:100sft
C3.Plastic Door/Win/Par
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glass-3mm thick-broken
105.000
sft
15.00
1575.00
Sub-Total(C3)
1575.00
169.53
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
5.500
sft
10.00
55.00
Sub-Total(E1)
55.00
5.92
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.500
No.
700.00
350.00
Skilled Labour
0.500
No.
600.00
300.00
Sub-Total(L1)
650.00
69.97
Total(1)
245.42
Add over head on Total(1)
3.5 %
8.59
Add Profit on Total(1)
10.0 %
24.54
Total(2)
33.13
Add VAT on Unit Price
5.5 %
1.93
Unit Price
35.06
Say
35
per sqm